Skip to main content

Groundwater Potential Survey Toteng/Sehitwa TGLP Area TB 10/2/5/90-91; Eleventh Month-End Report- By Geoflux (Pty) Ltd, 23 July - 22 August 1992

Price
BWP140.00

Supervision of borehole drilling, construction and pumping test works continued for the period from 23ru July to 22 August, marking the end of the field activity phase of the project. Two boreholes (the last of the project) were drilled and seven were pump tested. Alignment and verticality tests were carried out in fifteen boreholes. All project boreholes were levelled and fixed by G.P.S.